Commercial Solar Coventry

Commercial Solar Coventry

As part of a re-roof of a government building in Coventry, working for Graham Facilities Management we installed a 152.28kWp Solar system.

  • Project Type: Commercial Solar PV
  • Location: Coventry, Warwickshire
  • Estimated Annual Generation: 131,850kWh

Installed over 9 roofs, onto Slate, this 152.28kWp system used 423 x SunPower Maxeon 360w panels optimised by SolarEdge. The panels were mounted on a K2 rail system fixed to the roof using over 600 bespoke Nicholson fixings.

Working with the roofing company the Nicholson fixings were first installed before the slate and then followed by the rail, optimisers and panels at a second stage.

To complete the works bird guard was installed around the array.

Owing to very difficult access the optimised system is ideal for future maintenance as all panels can be monitored individually.